Process Is The Main Thing

@ Anatoly Belaychuk’s BPM Blog

Basic BPMN Assumption 4: Tasks Have Standard Duration and There Is A Way To Control It

Basic BPMN Assumptions:

  1. All information is stored
  2. Organization has a mechanism of tasks assignation and transfer
  3. Every task is accompanied by appropriate instruction
  4. Every task has standard duration and there is a way to control it

4. Every task has standard duration and there is a way to control it

Question: how do we show at the diagram that task should be accomplished in 2 hours?

Answer: normally we don’t need to model it. Just let’s agree once and forever that:

  1. standard duration can be set up for any task at the schema level (there is appropriate task attribute) and
  2. organization has some means to monitor actual vs. standard duration

If the process is implemented in BPMS then we may count on BAM (Business Activity Monitoring) - dynamic reports first displaying a bird’s-eye view of the process system then a detailed view by drilling-down up to a single process instance. Besides the system will likely provide automatic notifications about task assignation, expiration and withdrawal that will be sent by email to the performer or his/her boss (or rather both of them).

If the process is executed without BPMS then control would consume manager’s intellectual resources - meetings, phone calls, verbal communications… By the way getting rid of this headache is another, oftenly underestimated BPMS effects.

Anyway, this kind of control belongs rather to task management than to process management. After all, tasks may come not only from process but also from projects, ERP, cases or just ad-hoc. The options are many, but it’s always about standard vs. actual durations control.

It’s quite easy to model such control in BPMN:

To be consistent we should hook up every real task with a timer and a control task. Would it please you? Not me, for sure. Therefore I prefer to associate this kind of control with task management, not processes management.

What if a task is overdue? Let’s just assume there is some kind of a control system so a manager becomes aware of it and takes appropriate actions. To achieve this, we just specify the standard duration in the task attributes but don’t draw anything at the diagram.

By the way the overdue isn’t a crime. If we set up a standard duration equal to the mean value of the duration statistical distribution then it’d happen in about 50% cases (assuming that the distribution is close to the normal). It won’t mean the performer’s fault - just the tight standard duration. It’s better than setting a relaxed duration.

So use BPMN timers only when some non-trivial action (other than routine duration control) is needed.

Example 1: Creating a proposal. If the buyer set up a hard deadline and we have missed it then it doesn’t make sense to continue:

Example 2: Expectation of delivery. If goods have not arrived in due time, contact the transport company:

01/07/13 | Articles |    

Comments (2)

  1. Виктор 03/30/15 04:33 PM

    Судя по схеме, если груз не пришел в установленный срок, процесс обречён на неудачу.

  2. Anatoly Belychook 03/30/15 04:57 PM

    Почему же “обречен”? А развилка “ждем еще”?

Comments are closed

Copyright © 2008-2024 Anatoly Belychook. Thanks to Wordpress and Yahoo.  Content  Comments